3.1 Equipment Setup
)
The example given is for static operations.
Equipment setup
step-by-step
Step Description
1. Set up the tripod.
2. Mount and level the tribrach on the tripod.
3. Ensure that the tribrach is over the marker.
4. Place and lock the carrier in the tribrach.
5. Screw the antenna onto the carrier.
6. Check that the tribrach is still level.
7. Insert the batteries into the receiver.
)
Alternatively or in addition, to power the receiver externally, connect a
GEB171 battery to the port PWR on the receiver. When using the sensor
for real-time applications on construction machinery (machine automa-
tion), it is recommended to power the sensor externally.